The AD operations team received on Friday, 1 June – 12 days earlier than rescheduled – the green light from the AD injection kicker expert: beam could be injected again in the AD ring
The beam commissioning of the Antiproton Decelerator will start on 12 June, and the aim is to deliver antiprotons to the eagerly waiting AD-ELENA experiments on 30 June
With the Proton Synchrotron and its Booster accelerating protons to high energies again, the physics season can start at the ISOLDE radioactive ion beam facility and the Antimatter Factory
In the AD hall, a beam of H- ions has reached the GBAR and ALPHA experiments, marking the end of the installation of new transfer lines from the ELENA deceleration ring